Brisbane City, QLD

Cross River Rail — Roma Street Underground Station

TRSC anchor pull testing at Cross River Rail's Roma Street underground station — OPUS programme 001. CBGU JV principal contractor.

Building Background

The new Roma Street underground station is one of four new underground stations being delivered by Cross River Rail, the 10.2 km dual-track suburban rail line extension under construction beneath the Brisbane River and CBD. The Roma Street station is being constructed as part of the Tunnel, Stations and Development (TSD) package, which also includes the 5.9 km twin tunnels from the Southern Tunnel Portal near Dutton Park to the Northern Tunnel Portal in Spring Hill, and the four new underground stations at Boggo Road, Woolloongabba, Albert Street and Roma Street. The package is delivered by the CBGU JV — a joint venture of CPB Contractors, BAM International Australia, Ghella and UGL. The station comprises a 280 m long station cavern with up to 24.4 m excavated span and approximately 15 m of rock cover, five smaller connecting tunnels (adits) and three shafts, including a 20 m deep station box that accommodates the main station entrance, lifts and escalators. The cavern was excavated by sequential excavation in the Neranleigh-Fernvale Group rock mass — weakly metamorphosed sandstone (meta-greywacke and arenite), phyllite and subordinate quartzite and meta-basalt — within the regional Normanby Fault Zone, requiring heavier primary support and localised foundation treatment where intersecting the up-to-20 m wide fault zone of intact rock, rock breccia and clay gouge. The 20 m station box was fully excavated with 38,382 m³ of spoil removed, then constructed using 7,520 m³ of concrete and 14,700 t of steel up to ground level (L0); the 280 m cavern permanent lining required a further 13,100 m³ of concrete and 1,800 t of steel. Roma Street will become South East Queensland's most significant transport interchange, with more than 46,000 weekday users projected by 2036, linking suburban bus and rail, Brisbane Metro, and regional and interstate coach and train services.

TRSC Engagement Summary

TRSC's anchor testing engagement at Cross River Rail's Roma Street underground station is recorded under OPUS programme 001 — the practice's umbrella anchor testing programme — as Roma Cross River Rail Anchor Testing. The OPUS engagement category is Anchor Testing within the broader Engineering & Anchor Testing classification of programme 001. Anchor pull testing on a major underground station project of this kind supports verification of post-installed anchorage capacity for the wide range of station fit-out elements that interface with the new permanent reinforced concrete and shotcrete-lined structures of the station box, station cavern and connecting adits — including platform canopy steelwork, escalator and lift mounting frames, signalling and communications infrastructure, fire and life safety systems, mechanical plant restraint and station fit-out wall systems. Pull testing is performed in accordance with AS 5216-2021 (Design of post-installed and cast-in fastenings in concrete), with the recorded ultimate load and characteristic resistance compared against the design action effects derived from the relevant station-engineering loading codes. Programme 001 is recorded with active OPUS status reflecting the multi-site multi-phase nature of TRSC's anchor testing portfolio. RPEQ-certified anchor testing reports issued under programme 001 for the Roma Street engagement are held in the project record. The principal contractor for the Cross River Rail Tunnel, Stations and Development (TSD) package is the CBGU JV (CPB Contractors, BAM International Australia, Ghella and UGL).

Frequently Asked Questions

Engineering questions about Cross River Rail — Roma Street Underground Station

What is Cross River Rail Roma Street station?
Roma Street is one of four new underground stations being delivered by Cross River Rail, Brisbane's 10.2 km dual-track suburban rail line extension under the Brisbane River and CBD. It comprises a 20 m deep station box, a 280 m long station cavern with up to 24.4 m excavated span and approximately 15 m of rock cover, five connecting adits and three shafts, with platforms set 27 m below ground.
Who is delivering Cross River Rail at Roma Street?
The Tunnel, Stations and Development (TSD) package — including the Roma Street station — is delivered by the CBGU JV: a joint venture of CPB Contractors, BAM International Australia, Ghella and UGL, under appointment from the Cross River Rail Delivery Authority of the Queensland Government.
What did TRSC do at Roma Street?
TRSC's engagement at Roma Street is recorded under OPUS programme 001 (the practice's umbrella anchor testing programme) as Roma Cross River Rail Anchor Testing. Pull testing supports verification of post-installed anchorage capacity for station fit-out interfacing with the new reinforced concrete and shotcrete-lined structures, including platform canopy steelwork, escalator and lift mounting frames, and signalling and communications infrastructure.
What is the geology at Roma Street?
The cavern was excavated within the Neranleigh-Fernvale Group rock mass — weakly metamorphosed sandstone (meta-greywacke and arenite), phyllite and subordinate quartzite and meta-basalt — within the regional Normanby Fault Zone, which required heavier primary support and localised foundation treatment where intersecting the up-to-20 m wide fault zone of intact rock, rock breccia and clay gouge.